How to Compare Poultry Farm Equipment Quotations

Short answer: poultry quotations are almost never comparable as received. Rebuild every offer onto one specification — same bird numbers, same stocking density, same design temperature, same house dimensions, same Incoterm — then compare each package separately (structure, ventilation, cooling, heating, feeding, drinking, lighting, controls, power, egg or manure handling), add freight, duty, installation and commissioning, and list what each supplier excluded. The cheapest headline price is usually the offer with the smallest scope.

Three quotations for the same broiler house routinely differ by 40% or more, and most of that gap is scope, not price. One supplier quotes fans without stanchions, another includes a controller but not the sensors, a third prices FOB while the fourth prices CIF. Comparing the totals is meaningless until the offers sit on the same basis. This page describes the normalisation method used when a request is turned into a structured RFQ.

HatchMatch Group is an independent procurement platform — not a manufacturer, incubator supplier, EPC contractor, farm operator or lender. Named companies are described factually and are potential suppliers, not competitors to rank.

Step 1 — Fix the technical basis before comparing money

Every number in a quotation is derived from assumptions the supplier chose. If those assumptions differ, the prices are describing different projects. Before any commercial comparison, lock the basis and re-issue it to all bidders.

  • Bird type and production model (broiler, layer, pullet, breeder, dual-purpose)
  • Birds per house and number of houses, stated as placed birds not as capacity range
  • Stocking density in birds/m² or kg/m², including the target final live weight
  • House internal dimensions, ceiling height and structural system
  • Design outdoor temperature and relative humidity, plus the wet-bulb assumption used for evaporative cooling
  • Target air speed at bird level in tunnel mode and minimum ventilation rate
  • Electrical standard: voltage, phases, frequency and available grid reliability

Step 2 — Split the offer into packages

A single-line total hides everything. Require each bidder to price the same package structure so that a missing item is visible as a blank line rather than as a lower total.

  • Building and structure: frame, cladding, insulation value, doors, curtains, concrete interface
  • Ventilation: tunnel fans, minimum-ventilation fans, inlets, stanchions, static-pressure control
  • Cooling: pad area and thickness, pumps, recirculation, water treatment, or fogging nozzles and lines
  • Heating: type, capacity, fuel or gas train, distribution, flue and safety devices
  • Feeding: bins, augers, lines, pans or chains, feed weighing
  • Drinking: nipple lines, regulators, filtration, medicator, water meter
  • Lighting and controls: dimmable fixtures, climate controller, sensors, alarms, remote access
  • Layer or breeder specific: cages, aviary tiers, nests, egg belts, egg collection, grading interface
  • Manure and mortality handling, biosecurity equipment, standby power and solar

Step 3 — Convert to landed and commissioned cost

Equipment price is only part of the delivered cost. Bring every offer to the same delivery point and the same completion state, otherwise a low ex-works price wins on paper and loses on site.

  • Restate all offers to one Incoterm (commonly CIF or DAP the project site)
  • Add ocean or road freight, inland transport, insurance and demurrage risk
  • Add customs duty, VAT treatment and clearance costs in the destination country
  • Add erection labour, supervision days, travel, accommodation and visas
  • Add commissioning, calibration, operator training and handover documentation
  • Add first-year spare parts and consumables at quoted list prices

Step 4 — Read the exclusions before the prices

The exclusions list is the most informative page in most quotations, and it is usually the last one read. Common items pushed to the buyer are civil works, cable trays and power distribution from the panel to the equipment, water supply to the pad pump, gas piping, cranes and offloading, and local certification.

Where an exclusion is unavoidable, price it locally and add it to that bidder's column so the comparison stays complete.

Step 5 — Score the non-price terms

Two offers within a few percent on landed cost are effectively equal on money; the decision then lives in warranty, lead time and service reach.

  • Warranty length per package, and who administers claims in your country
  • Guaranteed spare-parts availability period and price list validity
  • Lead time to shipment and the penalty regime for delay
  • Payment terms and the security offered against advance payments
  • Reference installations of comparable capacity in a comparable climate
  • Local service presence: engineer response time, language, and whether the technician is employed or subcontracted

Where HatchMatch sits in this process

HatchMatch Group is an independent procurement platform, not a manufacturer, EPC contractor or lender. The buyer defines the project once; the request is normalised into a structured RFQ using exactly the basis described above and routed to qualified manufacturers and contractors, so the returned offers can be lined up line by line. Contract, delivery and warranty remain directly between the buyer and the chosen supplier.

Normalisation checklist applied to each bidder

Normalisation checklist applied to each bidder
Comparison lineWhat to normaliseTypical distortion if skipped
Capacity basisPlaced birds per house at a stated density and final weightA denser assumption makes the same house look cheaper per bird
VentilationInstalled airflow at a defined static pressure, not fan countFan quantity hides differing airflow and efficiency
CoolingPad area, thickness and design wet-bulb, or nozzle count and pressureUndersized pads appear as a lower cooling package price
HeatingInstalled kW against the coldest design conditionHeating is often sized for a milder assumption
AutomationController model, sensor count, alarm and remote access scopeA controller without sensors is not a control system
DeliveryOne Incoterm to the same siteEXW versus CIF can differ by 8–15% of equipment value
InstallationSupervision days versus full erection crewSupervision-only shifts labour cost to the buyer
Warranty and partsDuration, claim route, parts price list validityA shorter warranty is invisible in the total

Percentages and ranges are indicative planning figures, not quotations.

Buyer checklist before awarding

  • All bidders quoted on one written specification with the same design conditions.
  • Every package priced separately, with blanks visible rather than omitted.
  • All offers restated to one Incoterm and one delivery point.
  • Freight, duty, installation, commissioning and training added to every column.
  • Exclusions listed per bidder and locally priced where unavoidable.
  • Warranty holder, claim route and spare-parts price validity named in writing.
  • At least one reference installation of comparable capacity and climate contacted.
  • Lead time, delay penalty and payment security agreed before any advance payment.