Four routes compared
| Criterion | Manufacturer (direct) | Authorised dealer | Broker / trading company | EPC integrator |
|---|---|---|---|---|
| Who signs the supply contract | The producing factory, directly. | Authorised local company with a written mandate from the factory. | An intermediary that resells; the factory may have no contractual link to you. | A turnkey contractor that subcontracts equipment vendors. |
| Typical price position | Lowest ex-works cost, but excludes local services. | Factory price plus a service and stock margin. | Opaque markup; the underlying factory price is rarely disclosed. | Highest headline price; includes design, civil interface and coordination. |
| Warranty and claims | Direct factory warranty; claims handled cross-border. | Local warranty handling, usually faster in practice. | Depends entirely on whether the factory recognises the sale. | Single point of responsibility across all packages. |
| Spare parts availability | Genuine parts; lead time is the shipping time. | Often holds local stock for fast-moving items. | No stock obligation; repeat purchases may be difficult. | Managed as part of the O&M or service agreement. |
| Installation and commissioning | Supervision usually offered; local labour is the buyer's scope. | Typically includes or arranges installation crews. | Rarely included; often quoted as a separate unmanaged line. | Full installation, commissioning and handover included. |
| Multi-vendor coordination | Only their own system; interfaces are the buyer's problem. | Coordinates the brands it represents. | Bundles brands without engineering responsibility for interfaces. | Core function: ventilation, feeding, drinking, controls and civil works aligned. |
| Technical depth of answers | Engineering team available for airflow, density and layout questions. | Application knowledge for the local climate and building stock. | Frequently relays answers; inconsistencies appear over time. | Design-level: sizing, drawings and load calculations. |
| Best fit | Single-system purchases with an internal technical team. | Buyers who need local service and fast parts. | Rarely first choice; acceptable only when fully transparent and verifiable. | Complete farms and hatcheries where schedule risk dominates. |
This table describes typical market roles, not the quality of any named company. Individual counterparties vary; confirm the role in writing before contracting.
The hidden cost is coordination, not margin
Buyers often optimise the equipment line and absorb the coordination cost invisibly. On a complete broiler house, the interfaces between feeding lines, drinking lines, heating, tunnel ventilation and the climate controller are where schedule and performance risk live. Buying each package from its cheapest source is rational only when someone — internal engineering, a dealer or an integrator — owns those interfaces.
A useful test: write down every interface in the project and name the responsible party next to each. Any interface with no name is a risk the buyer has silently accepted.
Contract checklist before you commit
- •Confirm in writing which role the counterparty holds: manufacturer, authorised dealer, intermediary or contractor.
- •For dealers, request the written mandate or authorisation letter from the factory.
- •Name the warranty holder and the claims process for every package in the contract.
- •Fix spare-parts pricing and lead times for the first three years.
- •Define who performs installation, who supervises and who signs the commissioning protocol.
- •For multi-vendor scopes, assign interface responsibility explicitly.
- •Agree Incoterms, packing standard and documentation before the deposit.
- •Require the invoicing entity and the bank account name to match.