Financing guide
Acceptance and handover

Poultry equipment FAT, SAT and commissioning acceptance

A practical way to agree what 'accepted' means before purchase — at the factory, on site and at handover — so poultry farm and hatchery equipment can be checked against evidence rather than impressions.

Last updated: 2026-08-27

Short answer

Factory acceptance testing (FAT) checks equipment against the contract before dispatch; site acceptance testing (SAT) checks the installed system under site conditions before handover. Both work only if the criteria, evidence and responsible people are written into the RFQ and contract.

Define critical functions, test method, pass criteria, documents, training and spare parts for each system. Use the checklist builder below to draft them; contractual wording should be reviewed by your own legal adviser.

FAT
Factory acceptance test: verification at the manufacturer before shipping.
SAT
Site acceptance test: verification of the installed system on your site.
Punch list
A list of open defects or tasks agreed at handover, each with an owner and closing evidence.
Owner page
For the installation and commissioning process itself, see the installation guide.

For the installation and commissioning process itself, the installation guide is the main page. →

Poultry Equipment Acceptance Checklist Builder

Choose a system, mark the status of each item, then copy or print the checklist for your RFQ or site meeting.

Critical functions
  • Pass criteria written for each critical function
  • Alarm and notification test defined
  • Failure scenario test (power loss, sensor fault) defined
Documents
  • Drawings and wiring diagrams
  • Operating and maintenance manuals in the required language
  • Conformity documents for the destination market
  • Signed FAT protocol
Site conditions
  • Utilities connected and verified
  • Building complete for installation
  • Site climate conditions recorded during SAT
Training and spares
  • Operator training delivered and logged
  • Critical spare parts list agreed and delivered
  • Fault escalation route tested
Warranty and handover
  • Warranty start event agreed
  • Punch list with owners and dates
  • Handover signed by both parties

Accepted items: 0/16

Planning checklist only. It is not legal advice or a certification; adapt it with your engineer and adviser.

What is the difference between FAT and SAT?

They answer different questions and need different evidence.

FATSAT
WhereManufacturer's facilityYour site, after installation
PurposeConformity with contract and drawings before dispatchCorrect function under real utilities and climate
Typical checksDimensions, materials, wiring, control logic, test runsIntegration, alarms, safety devices, performance at site conditions
EvidenceTest protocol, photos or video, signed report, packing listCommissioning records, measurements, training log, signed acceptance
Who attendsBuyer or appointed inspector, manufacturerBuyer, installer, operator staff

Which evidence fields should each test record?

A test without recorded evidence is difficult to rely on later. Agree a template before the test.

  • System and serial or batch identification.
  • Function tested, method and pass criterion written beforehand.
  • Measured result, date, location and responsible person.
  • Deviations, agreed corrective action and closing evidence.
  • Signatures of buyer and supplier representatives.

What is a sensible commissioning sequence?

Commission from utilities upwards so each system is tested on a stable base.

  • Power, earthing, water and standby generation verified.
  • Individual components run (motors, fans, pumps, heaters).
  • Control system, sensors and alarm notifications tested.
  • Integrated systems run together (ventilation with heating and cooling, feeding with weighing).
  • Failure scenarios: power loss, sensor failure, alarm escalation.
  • Operator training and handover documents.

Which acceptance terms should be considered at procurement?

These are procurement considerations, not legal advice. Have contract wording reviewed by your adviser.

  • Which payment milestones depend on FAT, SAT or handover?
  • Is a retention or holdback considered until the punch list is closed?
  • Who pays for repeated tests after a failed FAT or SAT?
  • When does the warranty period start: dispatch, SAT or handover?
  • Which critical spare parts and response arrangements are included?
  • Which documents (manuals, wiring diagrams, conformity declarations) are delivered, and in which language?

How do I verify training and after-sales support?

Record who was trained on which system, and test the escalation route for a fault before the first flock: who answers, how parts arrive, and which remote access is agreed.

Step by step

How to set up acceptance before you buy

  1. 1

    List critical functions per system

    Ventilation, heating, cooling, feeding, drinking, egg collection, incubation, alarms.

  2. 2

    Write test methods and pass criteria

    State how each function is tested and what result counts as a pass.

  3. 3

    Put acceptance into the RFQ

    Ask every supplier to accept the same FAT, SAT and document requirements.

  4. 4

    Run FAT and record evidence

    Attend or appoint an inspector and sign the protocol before dispatch.

  5. 5

    Run SAT under site conditions

    Test integration and failure scenarios once utilities and building are complete.

  6. 6

    Close the punch list and hand over

    Agree owners and dates for open items, confirm training and spares, then sign handover.

Tools referenced here

Decision tools for the next step

All calculator outputs are indicative planning estimates, not guaranteed production, cost or performance results. Final figures are confirmed by suppliers, engineers and your own due diligence.

Financing: what HatchMatch does and does not do

HatchMatch is not a lender. With the buyer's consent, a defined project may be introduced to independent financing providers, who alone decide eligibility and terms. Nothing on this page is a financing offer.

Financing Disclaimer

HatchMatch Group is not a lender, bank, financial institution, credit provider, investment advisor, or regulated financial services provider. Financing requests submitted through this platform may, subject to user consent, be shared with independent third-party financing providers for evaluation purposes. Any financing approval, terms, pricing, underwriting, due diligence, eligibility criteria, provider requirements and contractual arrangements are determined solely by the financing provider. Financing is not guaranteed and remains subject to eligibility, compliance checks, and lender approval.

What this page does not decide

  • It is not legal advice; contract terms need review by your own adviser.
  • It does not certify conformity or replace inspection by qualified people.
  • It does not judge any specific supplier or product.
FAQ

Frequently asked questions

Add acceptance criteria to your supplier brief

Every brief is reviewed by a person; we aim to reply within two business days. Manufacturers decide independently whether to respond, and response times vary.