How long does it take to build a poultry farm? Plan the phases.
A commercial broiler farm of 20,000–60,000 birds typically runs about 10–14 months from concept to first placement; layer, hatchery, feed mill and processing projects run longer because equipment lead times are longer. Set your country, site climate, bird type, capacity and how far the project has already got — the planner re-sequences every phase using deterministic rules and shows dates. Indicative planning estimate, not a contractual schedule.
Inputs
Tunnel ventilation plus evaporative cooling to specify; rain season interrupts earthworks and concrete.
Full sequence from feasibility onwards.
Planning estimate only. Not a contractual schedule. Actual durations depend on suppliers, permitting, financing, weather and site conditions.
Indicative timeline
Target window is 52 weeks — ~12 weeks shorter than typical for this scope. Consider phasing, pre-ordering long-lead items or parallelising civil works with manufacturing.
- Phase 1Feasibility & site survey3 weeks · 19 Oct 2026 → 09 Nov 2026
Land, water, power, biosecurity buffer, market study.
- Phase 2Engineering & design5 weeks · 09 Nov 2026 → 14 Dec 2026
House layout, ventilation sizing, utilities, permits.
- Phase 3Supplier RFQ & selection6 weeks · 14 Dec 2026 → 25 Jan 2027
Structured RFQ, shortlist, factory references, contract.
- Phase 4Financing preparationparallel track8 weeks · 19 Oct 2026 → 14 Dec 2026
Bankable pack, ECA / leasing / DFI submission (parallel).
- Phase 5Manufacturing14 weeks · 25 Jan 2027 → 03 May 2027
Equipment fabrication and factory acceptance test (FAT).
- Phase 6Shipping & customs7 weeks · 03 May 2027 → 21 Jun 2027
Ocean freight, port clearance, inland transport.
- Phase 7Site preparation & civil15 weeks · 21 Jun 2027 → 04 Oct 2027
Earthworks, foundations, structure, roads, fencing.
- Phase 8Installation7 weeks · 04 Oct 2027 → 22 Nov 2027
Mechanical, electrical, ventilation, feed & water lines.
- Phase 9Testing & commissioning (SAT)3 weeks · 22 Nov 2027 → 13 Dec 2027
Site acceptance test, controls tuning, staff training.
Budget pages for this capacity
The schedule above sets the when. These pages set the how much — CAPEX bands, equipment scope and cost per bird place at the nearest standard capacities.