Load study and planning
Measure ventilation, cooling, lighting, feeding and water demand across the day; collect 12 months of electricity bills and diesel consumption; confirm roof or ground area and structural condition.
What a solar poultry project actually costs and how long each phase takes, before you commit to an RFQ round. Ranges are planning figures from comparable commercial projects — not commitments, and not a quotation. Send the enquiry at the bottom and a person reviews it before any supplier is contacted.
Measure ventilation, cooling, lighting, feeding and water demand across the day; collect 12 months of electricity bills and diesel consumption; confirm roof or ground area and structural condition.
One scope pack issued to a shortlist so bids are comparable on capacity, warranties, O&M and lead times. Financing runs in parallel, not after.
Foundations, mounting, equipment room, PV, inverters, batteries, cabling and switchgear, sequenced around flock cycles and utility connection approval.
Performance tests under real load, transfer behaviour on grid failure, BMS and genset sync tuning, operator training, provisional acceptance and start of warranty.
Full phase-gate detail, including what must exist before each phase starts, is on the solar project timeline page.
Installed cost bands by flock size and configuration, at typical 2026 equipment pricing. Storage, off-grid operation and difficult roofs push a project towards the top of its band.
| Site size | Configuration | PV | Storage | Installed cost | Simple payback |
|---|---|---|---|---|---|
| 10,000–25,000 birds | Grid-tied rooftop PV, no storage | 60–120 kWp | — | USD 55k–140k | 4–7 years |
| 25,000–60,000 birds | Grid-tied PV + small buffer storage | 120–260 kWp | 60–150 kWh | USD 140k–330k | 4–7 years |
| 60,000–120,000 birds | Hybrid PV + storage + existing genset sync | 260–550 kWp | 150–400 kWh | USD 330k–760k | 4–8 years |
| Off-grid site, any size | PV + storage + diesel backup | Sized to full 24h load | Night-load sized | +35–60% over grid-tied | 3–5 years vs diesel-only |
Reviewed by a person before anything is routed to suppliers. Minimum project value US$250,000. Financing, where relevant, is provided by independent third-party partners, subject to their approval.