Poultry project plan: sizing, cost, RFQ and proposal comparison in one page

Every calculator, the RFQ and the proposal-comparison step in the order a commercial poultry project actually needs them — each with worked figures from the same example farm, so you can see how one number feeds the next.

Worked example: 100,000-bird broiler farm, hot climate, grid + backup

The same project is carried through all six steps below.

Target capacity100,000 broilers per cycle
Houses4 tunnel houses, 120 m × 15 m (1,800 m² each)
Stocking density≈ 13.9 birds/m² (≈ 33 kg/m² at 2.4 kg live weight)
Cycles per year6 (35-day grow-out + 14-day turnaround)
ClimateDesign temperature 38 °C, tunnel ventilation + evaporative cooling
PowerGrid + diesel backup sized for full tunnel load

Step 1 of 6

Size the houses and the flock

Convert the capacity target into house dimensions, stocking density and number of houses. Every later number — ventilation, heating, feed, CAPEX — depends on this being fixed first.

Example figures

Birds per house25,000
House footprint120 m × 15 m = 1,800 m²
Density13.9 birds/m²
Houses required4

Permitted density depends on national regulation and welfare or certification schemes — confirm locally before freezing the layout.

Step 2 of 6

Size ventilation, cooling and heating

Tunnel airflow, pad area and brooding heat load drive fan counts, pad cooling and gas or biomass heater sizing — and a large share of both CAPEX and running cost.

Example figures

Tunnel air volume1,800 m² × 2.6 m ≈ 4,680 m³ per house
Target tunnel velocity2.2–2.5 m/s at market weight
Fans per house10 × 50" fans (≈ 40,000 m³/h each)
Evaporative pad≈ 45 m² per house at 1.8 m/s face velocity
Brooding heat≈ 350–450 kW per house at 38 °C swing design

Indicative sizing for comparison between suppliers — final selection belongs to the equipment engineer against local design temperatures.

Step 3 of 6

Estimate CAPEX and the investment envelope

Build a package-by-package CAPEX range before talking to any manufacturer, so a proposal that is 30% below the range is recognised as a scope gap, not a bargain.

Example figures

Houses (structure, insulation, floor)USD 900,000 – 1,150,000
Equipment (feed, drink, climate, controls)USD 640,000 – 820,000
Power, backup generator, distributionUSD 150,000 – 240,000
Site works, water, biosecurityUSD 180,000 – 300,000
Freight, installation, commissioningUSD 190,000 – 280,000
Indicative totalUSD 2.06M – 2.79M

AACE Class 4 order-of-magnitude range (−30% / +50%). Use it to test proposals, not to sign one.

Step 4 of 6

Model feed, FCR and operating cost

Feed is normally 60–70% of lifetime cost. A small FCR or energy difference outweighs most equipment price differences over ten years.

Example figures

Live weight per cycle100,000 × 2.4 kg = 240 t
FCR1.58
Feed per cycle≈ 379 t
Feed cost at USD 430/t≈ USD 163,000 per cycle
Annual feed cost (6 cycles)≈ USD 978,000
Effect of 0.05 FCR improvement≈ USD 31,000 per year

Benchmark assumptions only; substitute your own breed performance and local feed prices.

Step 5 of 6

Write one RFQ that every supplier answers identically

Freeze scope, quantities, standards, delivery terms and documentation in one document. Without it, the proposals that come back are not comparable and the whole exercise restarts.

Example figures

Scope line4 × tunnel-ventilated broiler houses, 25,000 birds each, turnkey equipment
Delivery termCIF Mombasa, Incoterms 2020
StandardsIP55 controls, CE marked fans, 230/400 V 50 Hz
Spares2 years of consumables and critical spares, priced separately
DocumentationLayout drawings, load schedule, O&M manuals, commissioning plan
ValidityPrice validity 90 days, delivery lead time stated in weeks

Anything left unstated in the RFQ becomes a variation order after the contract is signed.

Step 6 of 6

Normalise and compare the proposals

Bring every proposal onto one scope and one lifetime basis: add missing items back in, convert delivery terms, then compare energy, spares and downtime over ten years.

Example figures

Supplier A — quotedUSD 720,000 CIF
Supplier B — quotedUSD 648,000 FOB
B + freight, insurance, duty+ USD 74,000
B + generator and controls excluded from scope+ USD 61,000
B normalisedUSD 783,000
10-year energy difference (A more efficient)− USD 96,000 in A's favour

Illustrative normalisation to show the method — the headline price was not the lower total.

After the comparison

Once proposals are normalised, the remaining work is contractual: payment milestones, liquidated damages, spares pricing, commissioning acceptance and warranty scope. HatchMatch is an independent procurement platform — it does not manufacture equipment, does not act as an EPC contractor and does not guarantee supplier performance.

Estimates Only: This calculator is provided for general informational purposes only. Results are approximate and may contain errors, omissions, or outdated information. They do not constitute legal, financial, engineering, tax, technical, or professional advice. Users are solely responsible for independently verifying all calculations, specifications, prices, regulations, and requirements with qualified professionals before making any decisions. By using this calculator, you acknowledge that the website owners, operators, and affiliates accept no responsibility or liability for any loss, damage, or decisions resulting from its use.

Poultry project plan FAQs

Get a Free QuoteExplore Financing