Construction & EPC Delay

Risk that construction and commissioning slip beyond planned commercial operation date (COD), delaying revenue and increasing financing cost.

Audience: Buyer · Lender

When this guide applies

Greenfield poultry houses, hatcheries, feed mills and processing plants — any project with an EPC or turnkey contract.

Add to RFQ draft

Auto-fill mitigation & clause text into your RFQ

Select the risks you want covered. We'll pre-populate the RFQ description with the mitigations and paste-ready contract clauses — you can edit anything before submitting.

Mitigations + clauses will be inserted into the RFQ draft on the next step.
Interactive risk checklist

Tick the mitigations already in your plan

Coverage is severity-weighted, so covering a Critical risk moves the score more than a Low one.

Readiness score
0%
Early stage
0 of 9 mitigations · weighted 0/30
Site conditions differ materially from geotechnical assumptions High · Medium
Late equipment delivery blocks commissioning High · High
Permits and utility connections delayed beyond project schedule Critical · Medium

Site conditions differ materially from geotechnical assumptions

Severity: HighLikelihood: Medium
Impact: Foundation redesign, cost overrun 5–15% of civils budget
Mitigations
  • Commission an independent geotechnical survey before EPC contract signature — not after
  • Contract price is fixed except for a defined ground-conditions clause with quantified thresholds
  • Contingency of 5–10% of civils budget held by buyer, not EPC
RFQ / contract clause

"Ground conditions are treated as employer's risk only where they differ from the geotechnical baseline attached as Annex G. All other conditions are contractor's risk within the fixed price."

Late equipment delivery blocks commissioning

Severity: HighLikelihood: High
Impact: Idle civils, idle labour, deferred COD, loss of first placement window
Mitigations
  • Liquidated damages: typically 0.1–0.2% of contract value per day of delay, capped at 10%
  • Milestone dates for drawings, FAT, shipment and site acceptance — each with LDs, not just final COD
  • Long-lead items (breeder cages, evisceration lines, incubators) ordered before ground-breaking
RFQ / contract clause

"Liquidated damages for delay shall accrue at 0.15% of Contract Price per calendar day, capped at 10% of Contract Price, and shall be a genuine pre-estimate of the Employer's loss, not a penalty."

Permits and utility connections delayed beyond project schedule

Severity: CriticalLikelihood: Medium
Impact: Cannot operate even when facility is complete
Mitigations
  • Permit-tracking register maintained by buyer with named owner per permit
  • Utility connection (grid, water, gas) applied for at design freeze, not at commissioning
  • Diesel/LPG backup and water storage sized for 4 weeks of independent operation
RFQ / contract clause

"Utility connections and statutory permits are Employer's risk. EPC Contractor shall provide the technical documentation required for each application within the schedule set in Annex P."