• Suppliers indexed across 60+ countries
  • 140 vetted equipment manufacturers
  • EPC & OEM sourcing, project-scale
  • ECA & IFC-aware financing referrals
  • Comparative quotes typically 2–5 business days
Poultry Generator Sizing

Generator sizing calculator for poultry farms & hatcheries.

Enter your poultry load breakdown and the largest motor. We return standby kVA in three scenarios so you can specify a genset that actually restarts fans after a brownout.

Display
Phase
Voltage

Scenario cards, ATS ampacity and UPS sizing update to match. kW view converts via power factor pf = 0.8.

Loads (kW)

Total running load
103.0 kW
Conservative
259 kVA

All loads on. DOL inrush 7×. +15% margin. Hot-day worst case.

Running: 128.8 kVA
Peak w/ inrush: 225.0 kVA
Expected
197 kVA

85% diversity. 5× inrush. +10% margin.

Running: 109.4 kVA
Peak w/ inrush: 178.2 kVA
Optimistic
131 kVA

Soft-starters / VFDs. 70% diversity. +5% margin.

Running: 90.1 kVA
Peak w/ inrush: 124.5 kVA

Indicative only. Confirm final kVA with your supplier or electrical consultant against the single-line diagram and worst-case ambient temperature. Standby rating assumed.

Fuel-tank runtime

How long the generator runs on one tank at Expected running load (87.5 kW).

Fuel burn at Expected load24.5 L/h
Estimated backup runtime40.8 h

Battery kWh sizing

Battery bank to keep hatchery / SCADA / critical fans alive during ATS transfer or short outages.

Usable energy required20.0 kWh
Nominal battery bank23.6 kWh

ATS ampacity

Automatic Transfer Switch rating from the Expected genset (197 kVA) at 400 V, 3-phase, with a 25% continuous-duty margin, rounded up to the next standard frame.

System voltage (line-to-line, 3φ)400 V
Full-load current283 A
Sized current (×1.25)354 A
Recommended ATS frame400 A

UPS sizing (hatchery-critical)

Bridges the ATS transfer window and protects incubation controls / SCADA / alarms.

UPS apparent power22.2 kVA
Battery energy for hold-up3.33 kWh

First-pass sizing only. ATS frames, UPS topology (line-interactive vs online double-conversion) and battery chemistry (lithium vs VRLA) affect the final specification and should be confirmed by the supplier against your single-line diagram and site conditions.

Sensitivity — what changes the number most?

Drag the sliders — the tables below recompute instantly so you can see how DoD, inverter efficiency, autonomy, UPS pf and ATS margin move the recommended sizing.

Battery kWh — DoD × Autonomy

Nominal battery bank for a 20 kW critical load at inverter η = 0.94.

Autonomy1 h

Longer autonomy scales battery kWh linearly.

Depth of discharge (DoD)0.9

Lithium ~0.9, VRLA ~0.5. Halving DoD doubles the bank.

Inverter efficiency0.94

Modern hybrid inverters: 0.92–0.96.

DoD ↓ / Autonomy →0.5 h1 h2 h4 h
0.5021 kWh43 kWh85 kWh170 kWh
0.7015 kWh30 kWh61 kWh122 kWh
0.8013 kWh27 kWh53 kWh106 kWh
0.90← current12 kWh24 kWh47 kWh95 kWh

UPS & ATS sensitivity

How UPS kVA / hold-up energy and ATS frame move with your assumptions.

UPS output pf0.9

0.9 typical, 1.0 for unity-pf online double-conversion.

UPS hold-up10 min

Bridges ATS transfer + genset failure-to-start.

UPS kVA vs pf @ current critical load
UPS pf0.750.850.91
Apparent power26.7 kVA23.5 kVA22.2 kVA20.0 kVA
Hold-up energy vs minutes
Minutes5 min10 min15 min30 min
Battery energy1.67 kWh3.33 kWh5.00 kWh10.00 kWh
ATS frame vs continuous-duty margin
Margin×1.00×1.15×1.25×1.40
Frame400 A400 A400 A400 A

Default ×1.25 = NEC continuous-duty; current sizing draws 354 A → 400 A frame.

Turn a size into a shortlist

Send these numbers straight to a backup-power RFQ. Genset kVA, fuel-tank runtime, battery kWh, ATS frame and UPS kVA are prefilled into the buyer notes so suppliers quote against the same sizing brief.

Generator sizing — FAQ

How is generator kVA calculated for a poultry farm?

Take the total running kW of continuous loads (fans, cooling, lighting, feeders, drinkers, controllers), add starting inrush for the largest motor (typically 5–7× rated kW for direct-on-line fans), divide by generator power factor (~0.8), then add a diversity and safety margin. This calculator applies that logic across three scenarios.

Why three scenarios (Conservative / Expected / Optimistic)?

Conservative assumes all loads run simultaneously with full motor inrush (worst-case hot day). Expected uses a realistic diversity factor. Optimistic uses staggered fan start-up and soft-starters. Serious buyers order Conservative; Optimistic requires proven soft-start hardware.

Does this replace an electrical engineer's sizing?

No. This is a first-pass sizing tool for RFQ preparation. The final genset kVA must be confirmed by the supplier or an electrical consultant against your single-line diagram, VSD/soft-start strategy and worst-case ambient temperature.

What kVA does a 100,000-bird broiler farm typically need?

As an order-of-magnitude reference, a 100,000-bird tunnel-ventilated broiler complex generally sits between 250–500 kVA once fans, cooling, lighting, feeders and starting inrush are covered. Hatcheries scale with setter and hatcher count.

How do I estimate diesel generator runtime from fuel-tank size?

Diesel gensets burn roughly 0.25–0.30 L/kWh at 50–75% load. Runtime hours ≈ tank litres ÷ (running kW × 0.28). This calculator uses 0.28 L/kWh at the Expected running load; hot ambient, low load and old engines all increase specific fuel consumption.

How do I size a battery bank in kWh for a poultry farm?

Battery kWh ≈ critical load kW × autonomy hours ÷ (depth-of-discharge × inverter efficiency). For lithium at 90% DoD and 94% inverter efficiency, a 20 kW critical load needing 2 hours of ride-through works out to ~47 kWh nominal. Hatcheries typically size for 30–120 minutes; broilers for 15–60 minutes to cover ATS transfer plus fan restart.

How is ATS ampacity chosen?

The Automatic Transfer Switch must be rated at or above the generator's full-load amps at the site voltage. For 3-phase, A = kVA × 1000 ÷ (√3 × V). We add a 25% NEC-style continuous-duty margin and round up to the next standard frame (100/160/250/400/630/800/1250/1600/2000 A).

Do I need a UPS on top of a standby generator?

Yes for hatchery-critical loads (setter/hatcher controls, incubation ventilation, alarm and SCADA). A UPS bridges the 8–15 seconds an ATS needs to detect mains loss and transfer to genset, and protects electronics from switch-over transients. Broiler farms with tolerant controls can skip UPS on non-critical circuits.

Get QuotesFinancing